Back to projects

Nipigon Asset Management

Nipigon, Ontario

completeCapacity BuildingMRIF
Federal contribution
$3,966
Federal share33%

of $11.9K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 18, 2007
20072008
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Nipigon
Construction start
Jun 18, 2007(actual)
Construction end
Jul 28, 2008(actual)

Against the original forecast

  • Construction end6 weeks lateforecast Jun 15, 2008

Also in Nipigon