Nipigon Asset Management
Federal contribution
$3,966
Federal share33%
of $11.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedJun 18, 2007
20072008
Built
Approved 6 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Nipigon
- Construction start
- Jun 18, 2007(actual)
- Construction end
- Jul 28, 2008(actual)
Against the original forecast
- Construction end6 weeks lateforecast Jun 15, 2008
Also in Nipigon
- Nipigon Wastewater Treatment$3.5M
- Upgrading the Nipigon Sewage Treatment Plant to a Secondary Treatment Process$341.9K
- Churchill St. Linear Infrastructure Renewal$268.3K
- Nipigon Recreation Swimming Pool, Nipigon Community Centre Heating and Ventilation System$187.0K
- Restoration of existing storm sewer collection system, manhole, catch basins and storm sewer pipe.$104.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18085 in the federal list. How to read these figures.