Town of Kearney-Road Management Plan

Kearney, Ontario

completeCapacity BuildingMRIF
Federal contribution
$3,136
Federal share33%

of $9.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 27, 2007
200720082009
Built

Approved 7 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Kearney
Construction start
Jun 27, 2007(actual)
Construction end
Apr 16, 2009(actual)

Against the original forecast

  • Construction end10 months lateforecast Jun 15, 2008