Back to projects

Municipal Complex Retrofit and Expansion

Kearney, Ontario

completeVentilationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 1, 2022(actual)
Construction end
Aug 29, 2023(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 2, 2022
  • Construction end8 months lateforecast Dec 31, 2022

Also in Kearney

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59710 in the federal list. How to read these figures.