Municipal Complex Retrofit and Expansion
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Corporation of the Town of Kearney
- Construction start
- Sep 1, 2022(actual)
- Construction end
- Aug 29, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Aug 2, 2022
- Construction end8 months lateforecast Dec 31, 2022
Also in Kearney
- Rehabilitation of Arterial Road 518E$1.4M
- Main Street Beautification$730.4K
- Rehabilitate Septic System at 111 Main Street Location$18.8K
- Rehabilitate Septic System at 163 Main Street Location$16.2K
- Drilled well/water system at 111 Main Street. Upgrading of water system from lake source water supply to drilled well for human consumption/use$7.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59710 in the federal list. How to read these figures.