Main Street Beautification
Federal contribution
$730,423
Federal share100%
of $730.4K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 25, 2009
ApprovedOct 26, 2009
Built
Approved 4 months after the announcement.
- Program
- G8 Legacy Fund
- Ultimate recipient
- Corporation of the Town of Kearney
- Construction start
- Sep 14, 2009(actual)
- Construction end
- Nov 27, 2009(actual)
Also in Kearney
- Rehabilitation of Arterial Road 518E$1.4M
- Municipal Complex Retrofit and Expansion$80.0K
- Rehabilitate Septic System at 111 Main Street Location$18.8K
- Rehabilitate Septic System at 163 Main Street Location$16.2K
- Drilled well/water system at 111 Main Street. Upgrading of water system from lake source water supply to drilled well for human consumption/use$7.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33262 in the federal list. How to read these figures.