Drilled well/water system at 111 Main Street. Upgrading of water system from lake source water supply to drilled well for human consumption/use
Federal contribution
$7,500
Federal share50%
of $15.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the Town of Kearney
- Construction start
- Jun 23, 2017(actual)
- Construction end
- Oct 18, 2018(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 6, 2017
- Construction end2 months earlyforecast Dec 31, 2018
Also in Kearney
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48902 in the federal list. How to read these figures.