Muskoka Lakes Asset Management

Bracebridge, Ontario

completeCapacity BuildingMRIF
Federal contribution
$4,277
Federal share33%

of $12.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 27, 2007
200720082009
Built

Approved 7 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Muskoka Lakes
Construction start
Jul 1, 2007(actual)
Construction end
Mar 20, 2009(actual)

Against the original forecast

  • Construction end12 months lateforecast Mar 31, 2008