Replacement of Port Carling Wastewater Treatment Plant
Federal contribution
$4.4M
$4,401,667
Federal share33%
of $13.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201120132015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- District Municipality of Muskoka
- Construction start
- Jul 6, 2009(actual)
- Construction end
- Sep 4, 2015(actual)
Against the original forecast
- Construction end8 months lateforecast Dec 31, 2014
Also in Bracebridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24707 in the federal list. How to read these figures.