Back to projects

Muskoka Branch New Animal Shelter

Bracebridge, Ontario

completeOtherISF
Federal contribution
$596,667
Federal share33%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Construction start
Sep 13, 2010(actual)
Construction end
Aug 19, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 28, 2010

Also in Bracebridge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33329 in the federal list. How to read these figures.