Downtown Revitalization
Federal contribution
$800,315
Federal share91%
of $880.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 15, 2009
ApprovedNov 30, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- G8 Legacy Fund
- Ultimate recipient
- Corporation of the Town of Bracebridge
- Construction start
- Nov 30, 2009(actual)
- Construction end
- Jun 25, 2010(actual)