Riel Recreation Park

St. Albert, Alberta

completeSportMRIF
Federal contribution
$3.0M
$3,000,000
Federal share25%

of $12.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 17, 2007
200820092010
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of St. Albert
Construction start
Oct 9, 2007(actual)
Construction end
Mar 16, 2010(actual)

Against the original forecast

  • Construction start3 months earlyforecast Dec 31, 2007

Also in St. Albert

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18297 in the federal list. How to read these figures.