St Albert Servus Place Roofing and Lifecycle Replacement
Federal contribution
$2.2M
$2,239,242
Federal share74%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
Built
Approved 6 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of St. Albert
- Construction start
- May 18, 2021(actual)
- Construction end
- Sep 30, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast Feb 5, 2021
- Construction end2 months earlyforecast Nov 30, 2021
Also in St. Albert