St Albert Fowler Athletic Park Refurbishment
Federal contribution
$2.3M
$2,296,000
Federal share80%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of St. Albert
- Construction start
- Apr 16, 2021(actual)
- Construction end
- Nov 30, 2021(actual)
Against the original forecast
- Construction start2 weeks lateforecast Apr 1, 2021
- Construction end4 weeks lateforecast Oct 31, 2021
Also in St. Albert
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58489 in the federal list. How to read these figures.