NND Phase II Geothermal

Mayo, Yukon

completeGreen EnergyMRIF
Federal contribution
$857,880
Federal share29%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
201120122013201420152016
Built

Approved 5.8 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
May 13, 2010(actual)
Construction end
May 31, 2013(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Apr 1, 2010
  • Construction end2.2 years lateforecast Mar 31, 2011