NND Phase II Geothermal
Federal contribution
$857,880
Federal share29%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
201120122013201420152016
Built
Approved 5.8 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- First Nations of Na-Cho Nyak Dun
- Construction start
- May 13, 2010(actual)
- Construction end
- May 31, 2013(actual)
Against the original forecast
- Construction start6 weeks lateforecast Apr 1, 2010
- Construction end2.2 years lateforecast Mar 31, 2011
Also in Mayo
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18556 in the federal list. How to read these figures.