New Water Delivery Fill Station
Federal contribution
$565,676
Federal share28%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.2 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- First Nations of Little Salmon Carmacks
- Construction start
- Apr 1, 2010(actual)
- Construction end
- Jul 31, 2012(actual)
Against the original forecast
- Construction start6 months lateforecast Oct 1, 2009
- Construction end16 months lateforecast Mar 31, 2011
Also in Carmacks
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18576 in the federal list. How to read these figures.