Sewer Line Replacement

Teslin, Yukon

completeWastewaterMRIF
Federal contribution
$38,000
Federal share33%

of $114.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 7, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Teslin
Construction start
Jul 3, 2007(actual)
Construction end
Jun 30, 2008(actual)

Against the original forecast

  • Construction start11 months lateforecast Aug 1, 2006
  • Construction end8 months lateforecast Oct 31, 2007

Also in Teslin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18619 in the federal list. How to read these figures.