Palestre Arena HVAC Upgrade
Federal contribution
$60,868
Federal share25%
of $243.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 20, 2008
200820092010
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Gravelbourg
- Construction start
- Dec 14, 2007(actual)
- Construction end
- Dec 22, 2009(actual)
Against the original forecast
- Construction end3 months earlyforecast Mar 31, 2010
Also in Gravelbourg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18622 in the federal list. How to read these figures.