Arena Upgrades and Improvements

Meadow Lake, Saskatchewan

completeGreen EnergyMRIF
Federal contribution
$125,000
Federal share18%

of $703.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2008
2008
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Meadow Lake
Construction start
Dec 14, 2007(actual)
Construction end
Nov 18, 2008(actual)

Against the original forecast

  • Construction start4 months earlyforecast Apr 1, 2008
  • Construction end4 months earlyforecast Mar 31, 2009

Also in Meadow Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18636 in the federal list. How to read these figures.