Aquatic Centre Solar Pool Heating

Biggar, Saskatchewan

completeGreen EnergyMRIF
Federal contribution
$27,623
Federal share25%

of $110.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 4, 2008
20082009
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Biggar
Construction start
Dec 14, 2007(actual)
Construction end
Feb 27, 2009(actual)

Against the original forecast

  • Construction end5 weeks earlyforecast Mar 31, 2009