Arena Renovations
Federal contribution
$24,455
Federal share25%
of $97.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 21, 2008
200820092010
Built
Approved 5 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Oxbow
- Construction start
- Dec 14, 2007(actual)
- Construction end
- Mar 7, 2010(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Mar 31, 2010
Also in Oxbow
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18765 in the federal list. How to read these figures.