Back to projects

Town of Oxbow - Wastewater System Capacity Building

Oxbow, Saskatchewan

completeWastewaterGIS
Federal contribution
$1.5M
$1,521,968
Federal share40%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2021
20222023
Built

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Oxbow
Construction start
Jun 8, 2021(actual)
Construction end
Dec 31, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2021
  • Construction end6 months lateforecast Jun 30, 2022

Also in Oxbow

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57426 in the federal list. How to read these figures.