Highway 18 Glen Ewen to Oxbow
Federal contribution
$1.2M
$1,177,750
Federal share50%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built
Approved 8 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Apr 26, 2010(actual)
- Construction end
- May 29, 2010(actual)
Against the original forecast
- Construction end2 months earlyforecast Jul 31, 2010
Also in Oxbow
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33298 in the federal list. How to read these figures.