Water Supply Improvements to Supply Wells #3 & #5

Haines Junction, Yukon

completeDrinking WaterMRIF
Federal contribution
$147,541
Federal share33%

of $442.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2009201120132015
Built

Approved 7.7 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Haines Junction
Construction start
Apr 1, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start22 months lateforecast Jun 1, 2008
  • Construction end3.2 years lateforecast Sep 1, 2008