Water Supply Improvements to Supply Wells #3 & #5
Federal contribution
$147,541
Federal share33%
of $442.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2009201120132015
Built
Approved 7.7 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Haines Junction
- Construction start
- Apr 1, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start22 months lateforecast Jun 1, 2008
- Construction end3.2 years lateforecast Sep 1, 2008