City of Brandon / Brandon YMCA Joint Recreation Facility
Federal contribution
$2.3M
$2,313,000
Federal share33%
of $6.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2009201120132015
Built
Approved 7.7 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Brandon
- Construction start
- Jan 1, 2011(actual)
- Construction end
- Sep 18, 2012(actual)
Against the original forecast
- Construction start3.1 years lateforecast Nov 23, 2007
- Construction end2.2 years lateforecast Jun 22, 2010
Also in Brandon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 19424 in the federal list. How to read these figures.