Repair work on Lacroix Blvd, south end (between Streets 127 and 135 and Streets 159 and 193.)

Saint-Georges, Quebec

completeDrinking WaterMRIF
Federal contribution
$427,700
Federal share33%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 3, 2008
20092010
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Saint-Georges
Construction start
Jun 16, 2008(actual)
Construction end
Dec 31, 2009(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 30, 2008

Also in Saint-Georges

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 19504 in the federal list. How to read these figures.