Construction of a retaining wall (Quai Pinon)

Saint-Georges, Quebec

completeDisaster MitigationSCF
Federal contribution
$6.6M
$6,589,069
Federal share33%

of $19.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2017
2018201920202021
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Saint-Georges
Construction start
Apr 18, 2017(actual)
Construction end
Mar 24, 2021(actual)

Against the original forecast

  • Construction start12 months earlyforecast May 1, 2018
  • Construction end16 months lateforecast Nov 30, 2019