South/West Quadrant Watermain Replacement

LaSalle, Ontario

completeDrinking WaterMRIF
Federal contribution
$2.7M
$2,690,000
Federal share33%

of $8.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 19, 2008
2008200920102011
Built

Approved 5 weeks after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Lasalle
Construction start
May 28, 2008(actual)
Construction end
Sep 16, 2011(actual)

Against the original forecast

  • Construction end18 months earlyforecast Mar 31, 2013