Improvements to Malden Road
Federal contribution
$3.4M
$3,416,633
Federal share33%
of $10.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Lasalle
- Construction start
- Jul 19, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 21, 2010
Also in LaSalle
- Disaster Mitigation and Infrastructure Enhancement$14.8M
- Construction of Laurier Road Extension and the Hwy 3/Hwy 401/Windsor-Essex Parkway Interchange$6.0M
- South/West Quadrant Watermain Replacement$2.7M
- Front Road Infrastructure and Public Safety Renewal$1.8M
- Reaume Road and Bouffard Road Watermain Replacement$1.6M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28083 in the federal list. How to read these figures.