Front Road Infrastructure and Public Safety Renewal

LaSalle, Ontario

completeHighways and RoadsISF
Federal contribution
$1.8M
$1,807,795
Federal share30%

of $6.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 22, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of LaSalle
Construction start
Jun 14, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2010
  • Construction end4 weeks lateforecast Sep 30, 2011