Replacement of Sewage Forcemains
Federal contribution
$799,162
Federal share33%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2008
2009
Built
Approved 8 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Parry Sound
- Construction start
- May 28, 2008(actual)
- Construction end
- Nov 30, 2009(actual)
Against the original forecast
- Construction end16 months earlyforecast Mar 31, 2011
Also in Parry Sound
- Highway 69 Project; Four-Lane Expansion from Highway 529 to Highway 522$120.0M
- Highway 69 Project; 4-Lane Expansion, Highway 559 Northerly$49.3M
- West Parry Sound Area Recreation and Culture Centre joint project between 7 Municipalities and 2 First Nations Communities$12.8M
- Upgrading of Parry Sound Wastewater Treatment Plant$5.3M
- Highway 518 - East of Highway 400 towards Orrville$2.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 19784 in the federal list. How to read these figures.