Nunavut - Capacity Building
Federal contribution
$44,613
Federal share50%
of $89.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20082010201220142016
Built
Approved 7.9 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Government of Nunavut
- Construction start
- Apr 23, 2008(actual)
- Construction end
- Mar 31, 2009(actual)
Against the original forecast
- Construction start3 weeks lateforecast Apr 1, 2008
- Construction end12 months earlyforecast Mar 31, 2010
Also in Iqaluit