Sewage Lift Station #1
Federal contribution
$1.5M
$1,538,362
Federal share33%
of $4.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 20, 2009
200920102011201220132014
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Weyburn
- Construction start
- Jul 31, 2009(actual)
- Construction end
- Mar 7, 2014(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2009
- Construction end3 weeks earlyforecast Mar 31, 2014
Also in Weyburn
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22114 in the federal list. How to read these figures.