Back to projects

Water Meter and Service Line Upgrade

Weyburn, Saskatchewan

completeDrinking WaterCWWF
Federal contribution
$2.7M
$2,719,750
Federal share50%

of $5.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
201820192020
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Weyburn
Construction start
Aug 16, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Sep 1, 2017
  • Construction end5 weeks lateforecast Feb 28, 2020

Also in Weyburn