Water Meter and Service Line Upgrade
Federal contribution
$2.7M
$2,719,750
Federal share50%
of $5.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
201820192020
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Weyburn
- Construction start
- Aug 16, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Sep 1, 2017
- Construction end5 weeks lateforecast Feb 28, 2020