Weyburn Water Reservoir Expansion
Federal contribution
$5.3M
$5,300,666
Federal share33%
of $15.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 4, 2016
2017201820192020
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- City of Weyburn
- Construction start
- Feb 15, 2017(actual)
- Construction end
- Aug 31, 2020(actual)
Against the original forecast
- Construction end14 months lateforecast Jun 30, 2019
Also in Weyburn
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46576 in the federal list. How to read these figures.