Hamlet of Sunset View Beach- New WTP
Federal contribution
$322,700
Federal share33%
of $968.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 20, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Rural Municipality of Mervin
- Construction start
- Sep 15, 2009(actual)
- Construction end
- Jun 30, 2011(actual)
Against the original forecast
- Construction start5 months lateforecast May 1, 2009
- Construction end9 months earlyforecast Mar 31, 2012
Also in Turtleford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22152 in the federal list. How to read these figures.