Town of Turtleford Spray and Play
Federal contribution
$63,000
Federal share40%
of $157.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2021
2021
Built
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Turtleford
- Construction start
- May 25, 2021(actual)
- Construction end
- Aug 13, 2021(actual)
Against the original forecast
- Construction start10 months earlyforecast Apr 1, 2022
- Construction end11 months earlyforecast Jun 30, 2022
Also in Turtleford