Federal contribution
$875,031
Federal share60%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2022
today
20232024202520262027
BuiltForecast

Approved 5 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Town of Turtleford
Construction start
Feb 1, 2023(actual)
Construction end
Sep 30, 2027(forecast)