Port Alberni - China Creek Watermain Replacement Phase 2

Port Alberni, British Columbia

completeDrinking WaterCC
Federal contribution
$583,333
Federal share33%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 7, 2009
201020112012
Built

Approved 3 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Port Alberni
Construction start
Sep 1, 2009(actual)
Construction end
Nov 30, 2011(actual)

Against the original forecast

  • Construction start7 months lateforecast Feb 12, 2009
  • Construction end4 months earlyforecast Mar 31, 2012

Also in Port Alberni

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22167 in the federal list. How to read these figures.