Port Alberni - Dry Creek Improvements

Port Alberni, British Columbia

completeDisaster MitigationCC
Federal contribution
$912,166
Federal share33%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20152016
Built

Approved 24 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Port Alberni
Construction start
Jul 1, 2015(actual)
Construction end
Mar 31, 2016(actual)

Against the original forecast

  • Construction start12 months lateforecast Jul 1, 2014
  • Construction end9 months earlyforecast Dec 31, 2016

Also in Port Alberni

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44902 in the federal list. How to read these figures.