Port Alberni - Connect the Quays Multi-Modal Pathway

Port Alberni, British Columbia

completeActive TransportationCCRIS
Federal contribution
$962,220
Federal share28%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 11, 2022
2022202320242025
Built

Approved 2 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
City of Port Alberni
Construction start
Aug 14, 2023(actual)
Construction end
Dec 16, 2024(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 2, 2023
  • Construction end2 weeks lateforecast Dec 1, 2024