Port Alberni - Connect the Quays Multi-Modal Pathway
Port Alberni, British Columbia
Federal contribution
$962,220
Federal share28%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
2022202320242025
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Port Alberni
- Construction start
- Aug 14, 2023(actual)
- Construction end
- Dec 16, 2024(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 2, 2023
- Construction end2 weeks lateforecast Dec 1, 2024