Lagoon Upgrade

Tignish, Prince Edward Island

completeWastewaterCC
Federal contribution
$13,733
Federal share27%

of $50.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 28, 2009
2010
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Community of Tignish
Construction start
Jul 28, 2010(actual)
Construction end
Sep 30, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 10, 2010