Back to projects

Wellfield Site No. 2 Development

Tignish, Prince Edward Island

completeDrinking WaterCC
Federal contribution
$15,761
Federal share17%

of $93.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 28, 2009
2010
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Community of Tignish
Construction start
Nov 12, 2009(actual)
Construction end
Aug 13, 2010(actual)

Also in Tignish

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22313 in the federal list. How to read these figures.