Port Alice Community Centre Upgrade

Port Alice, British Columbia

completeRecreationCC Top Up
Federal contribution
$345,500
Federal share18%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Village of Port Alice
Construction start
Nov 20, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Sep 23, 2009