Back to projects

Port Alice Wastewater Treatment Plant Upgrade

Port Alice, British Columbia

completeWastewaterCWWF
Federal contribution
$525,210
Federal share50%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Port Alice
Construction start
Jan 3, 2017(actual)
Construction end
Mar 31, 2019(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 10, 2017
  • Construction end3 months lateforecast Dec 31, 2018

Also in Port Alice

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47694 in the federal list. How to read these figures.