Port Alice Wastewater Treatment Plant Upgrade
Federal contribution
$525,210
Federal share50%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 30, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Port Alice
- Construction start
- Jan 3, 2017(actual)
- Construction end
- Mar 31, 2019(actual)
Against the original forecast
- Construction start3 months earlyforecast Apr 10, 2017
- Construction end3 months lateforecast Dec 31, 2018
Also in Port Alice
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47694 in the federal list. How to read these figures.