Port Alice Water Tank Replacement
Federal contribution
$230,099
Federal share50%
of $460.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Port Alice
- Construction start
- Jul 19, 2017(actual)
- Construction end
- Mar 15, 2018(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Aug 14, 2017
- Construction end2 weeks lateforecast Feb 28, 2018
Also in Port Alice
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49842 in the federal list. How to read these figures.