Water Transmission & Distribution Main Replacements
Federal contribution
$500,487
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 12, 2008
20092010
Built
Approved 7 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Digby
- Construction start
- Apr 6, 2009(actual)
- Construction end
- Oct 16, 2010(actual)
Against the original forecast
- Construction start4 weeks earlyforecast May 1, 2009
- Construction end5 months earlyforecast Mar 31, 2011
Also in Digby
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22360 in the federal list. How to read these figures.