Dorintosh West Grid Road Upgrade
Federal contribution
$245,071
Federal share33%
of $735.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 20, 2009
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Rural Municipality of Meadow Lake
- Construction start
- Aug 7, 2009(actual)
- Construction end
- Oct 15, 2009(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2009
- Construction end2.5 years earlyforecast Mar 31, 2012
Also in Meadow Lake
- Meadow Lake Tribal Council Bioenergy$52.5M
- City of Meadow Lake - Recreation & Civic Centre$14.9M
- Sewage replacement and relocation for Meadow Lake sewage lagoon$8.0M
- Water Quality - Organic Removal Upgrades to Water Treatment Plant$1.6M
- SaskWater - Meadow Lake - Water Treatment Plant Actiflo Clarification$990.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22564 in the federal list. How to read these figures.