Replacement Bridge

Prince Albert, Saskatchewan

completeHighways and RoadsCC
Federal contribution
$155,904
Federal share33%

of $467.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 20, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Construction start
Dec 17, 2009(actual)
Construction end
May 30, 2011(actual)

Against the original forecast

  • Construction start8 months lateforecast May 1, 2009
  • Construction end10 months earlyforecast Mar 31, 2012

Also in Prince Albert

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22600 in the federal list. How to read these figures.