3rd Meridian Road Reconstruction
Federal contribution
$447,992
Federal share33%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 20, 2009
20092010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Rural Municipality of Prince Albert
- Construction start
- Sep 24, 2011(actual)
- Construction end
- Aug 20, 2013(actual)
Against the original forecast
- Construction start2.4 years lateforecast May 1, 2009
- Construction end2 months earlyforecast Oct 31, 2013
Also in Prince Albert