Taylor Local Roads Rehabilitation
Federal contribution
$1.2M
$1,169,604
Federal share33%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2009
2009201020112012
Built
Approved 5 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- District of Taylor
- Construction start
- Jul 8, 2009(actual)
- Construction end
- Mar 31, 2012(actual)