Taylor - Wastewater Treatment Plant: Solids Dewatering

Taylor, British Columbia

underwayWastewaterGIS
Federal contribution
$1.3M
$1,258,960
Federal share40%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 18, 2023
202420252026
BuiltForecast

Approved 8 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
District of Taylor
Construction start
May 7, 2025(actual)
Construction end
Feb 28, 2026(forecast)